Nanaimo city council will have another look at borrowing almost $77 million to fund upgrades to its public works yard.
Three readings are on the agenda for council’s Feb. 23 meeting of a borrowing bylaw that would allow the project to move ahead.
The total project cost would be $77 million, with $76.6 million set to come from long-term borrowing, according to documents prepared for council by city staff.
Staff were directed to proceed with design work in September 2025, with $1.8 million allocated for the work. A preliminary schedule shows construction could start late this year and the project could be completed in 2029.
The city has failed to get electoral approval for borrowing the funds three times through alternate approval processes and will now revisit it with changes to council’s borrowing policy and provincial rules.
BACKGROUND: Province doubles municipal borrowing limits to speed up infrastructure projects
In June, the province increased allowable borrowing without electoral approval for municipalities, but Mayor Leonard Krog said it would not affect large projects such as the public works yard.
BACKGROUND: Nanaimo mayor welcomes provincial borrowing changes for infrastructure
City staff said the province increasing the approval-free liability zone from five per cent to 10 per cent of sustainable and controllable revenues is what allows council to approve the project, along with changes to the borrowing policy council made in October. Council made electoral approval optional if borrowing falls within the provincial approval-free liability zone.
The staff report says the city’s 2024 sustainable and controllable revenues were $246.8 million and 10 per cent for the approval-free liability threshold is $24.7 million. The total liability servicing cost including new borrowing would be $11.9 million.
“As the proposed borrowing falls within the approval-free zone permitted under provincial legislation — and in accordance with the city’s debt management policy — electoral approval is not required,” the staff report says.
According to the staff report, the project will add about $121 annually to an average home with property taxes, water and sewer rate increases. Taxes were estimated to increase about $11 per $100,000 of assessed value.
Council will discuss and vote on the borrowing bylaw at its Feb. 23 meeting.